How to Edit Project Commencement and Completion Dates
How to add or edit the Project Commencement and Completion Dates in the Project Schedule.
Overview
When a project is created, INGENIOUS.BUILD automatically generates a Project Schedule with the Project Commencement and Project Completion milestones. These dates can be edited later from within the schedule.
Note: If you didn't select a Project Commencement and Completion Date when creating the project, a yellow warning triangle appears on the milestones prompting you to add start dates for both.
Process
Understand the system-generated Project Schedule
When a project is created, INGENIOUS.BUILD automatically generates a Project Schedule containing the Project Commencement and Project Completion milestones. The dates on these milestones come from the values entered during Step 3: Project Information of project creation.
Edit the Project Commencement and Completion Dates
-
Navigate to the Main Project Schedule.
-
Click Edit in the top right of the schedule.
-
Click the milestone to edit: Project Commencement Date or Project Completion Date.
-
Select the appropriate Start Date.
-
Click Update & Publish to save and share the changes.
Note: Milestones are considered a point in time and not a period, so an End Date cannot be entered. To save changes without publishing, click Save as Draft — draft updates are visible only to you until published.
If the project does not have a Project Schedule yet
-
Click Create New Schedule at the top right of the Schedule module.
-
Choose to start from scratch or import a schedule.
-
The Project Commencement and Project Completion dates are generated automatically. Follow the steps above to assign dates to these milestones.
-
Click Publish to make the schedule visible to others.
Who can edit the Project Commencement and Completion Dates
-
Anyone listed as a Project Member in the project directory can edit a system-generated schedule.
-
For a manually created schedule, only users the schedule has been shared with can view or edit it.